Search Legislation

The Water Resources (Environmental Impact Assessment) Regulations (Northern Ireland) 2005

 Help about what version

What Version

 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made).

  1. Introductory Text

  2. Expand +/Collapse -

    PART 1 GENERAL

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Application

  3. Expand +/Collapse -

    PART 2 PRE-APPLICATION PROCEDURES & ASSESSMENT OF RELEVANT PROJECTS

    1. 4.Determination whether a project is a relevant project

    2. 5.Environmental statement to be provided in relation to an application

    3. 6.Environmental statement, and opinions of the Department on the contents of an environmental statement

  4. Expand +/Collapse -

    PART 3 CONSENT

    1. 7.The application

    2. 8.Publicity for an application

    3. 9.Determination of application and notice of determination

    4. 10.Department’s decision on an application for consent

    5. 11.Revocation or modification of consent

  5. Expand +/Collapse -

    PART 4 PROHIBITION NOTICES

    1. 12.Prohibition notices

    2. 13.Penalties for contravention of a prohibition notice

  6. Expand +/Collapse -

    PART 5 PROJECTS LIKELY TO AFFECT OTHER MEMBER STATES

    1. 14.Projects likely to have significant effects on the environment in another Member State

    2. 15.Projects in another Member State likely to have significant transboundary effects

  7. Expand +/Collapse -

    PART 6 OFFENCES & APPEALS IN CONNECTION WITH CONSENT, REVOCATION, MODIFICATION AND PROHIBITION NOTICES

    1. 16.Restriction on commencing a relevant project

    2. 17.Appeals in relation to consent

    3. 18.Appeals in relation to revocation and modification notices

  8. Expand +/Collapse -

    PART 7 REGISTERS

    1. 19.Register of environmental statements and further information

  9. Signature

    1. Expand +/Collapse -

      SCHEDULE 1

      SELECTION CRITERIA FOR RELEVANT PROJECTS

      1. 1.Characteristics of projects

      2. 2.Location of projects

      3. 3.Characteristics of the potential impact

    2. Expand +/Collapse -

      SCHEDULE 2

      INFORMATION ABOUT PROPOSED PROJECT

      1. 1.A description of the project, including in particular –

      2. 2.An outline of the main alternatives studied by the developer...

      3. 3.A description of the aspects of the environment likely to...

      4. 4.A description (which shall cover the direct effects and any...

      5. 5.A description of the measures envisaged to prevent, reduce and...

      6. 6.A non-technical summary of the information provided under the above...

      7. 7.An indication of any difficulties (technical deficiencies or lack of...

  10. Explanatory Note